1 |
Provision of professional engineering services for the Mkhondo AGRI-HUB |
Review the current state of the project and Redesign. Supervise the planning, Coordination and implementation of Mechanical engineering duties (HVAC, Wet Services and Fire Protection) |
GS Fencing - Contractor |
2018/12/09 to 2019/12/15 |
2 |
Mechanical design review of a welded stand, Receiving warehouse |
Review the design, write a report with recommendations and sign-off drawings. |
Vele Engineering |
2019/10/06 to 2019/10/09 |
3 |
Mechanical design review of a vertical stand for hydraulic cylinders
|
Review the design, write a
report with recommendations
and sign-off drawings.
|
Vele
Engineering
|
2019/10/13
to
2019/10/16
|
4 |
Mechanical design
review of a pallet
|
Review the design, perform
FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Vele
Engineering
|
2019/11/01
to
2019/11/06
|
5 |
Mechanical design
review and FEM analysis of an extension towbar
|
Review the design, perform
FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/11/08
to
2019/11/13
|
6 |
Mechanical design
Review, structural and FEM analysis of an extension towbar
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/11/12
to
2019/12/02
|
7 |
Mechanical design
of a vertical sliding door drive mechanism
|
Review the current status, perform design calculations, design 3-D model, write a report. |
Kalahari
Project
Consultants
|
2019/11/13
to
2019/11/20
|
8 |
Mechanical design
Review, structural and FEM analysis of a water tank stand
|
Review the design, perform
Structural/FEM analysis, write a reportProje
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/11/21
to
2019/11/26
|
9 |
Mechanical design
Review, structural and FEM analysis of a crawl beam
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/01
To
2019/12/11
|
10 |
Mechanical design
Review, structural and FEM analysis of an overhead crane service platform
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/09
to
2019/12/19
|
11 |
Mechanical design
Review, structural and FEM analysis of an overhead crane service platform
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/09
to
2019/12/23
|
12 |
Mechanical design
Review, structural and FEM analysis of an overhead crane service platform
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/09
to
Ongoing
|
13 |
Mechanical design
Review, structural and FEM analysis of a Cummins engine stand
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/11
To
2019/12/19
|
14 |
Mechanical design
Review, structural and FEM analysis of an MTU engine stand
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/11
to
2019/12/19
|
15 |
Mechanical design
Review, structural and FEM analysis of an electrical workshop staircase
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/11
to
2019/12/30
|
16 |
Mechanical design
Review, structural and FEM analysis of a sivos admin office, new roof
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/11
to
2020/01/06
|
17 |
Mechanical design
Review, structural and FEM analysis of an overhead crane F900-G84 service platform
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/24
to
2019/12/26
|
18 |
Mechanical design
Review and SWL sizing of a cyclone plant crawl beam
|
Review the design, perform design calculations and FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Kalahari
Project
Consultants
|
2019/12/18
to
2020/02/11
|
19 |
Mechanical design
Review, structural and FEM analysis of the Expansion structure
|
Review the design, perform
Structural/FEM analysis, write a report
with recommendations and
sign-off drawings.
|
Mamolady’s |
2020/02/14
to
2020/04/09
|